Payment Notices & Pay less Notices

Payment Notices & Pay less Notices


What is a pay less notice?

Pay Less Notice is often available as a template, depending on how many companies are delivering it to customers. The Act (apart from all JCT contracts), however, does require a paid notice that meets the required minimum criteria. JCT contracts have to provide detailed information that will enable a recipient to understand:


What does a Pay Less Notice look like?

JCT contracts are required that a Pay Less Notice meet minimum requirements. They include the sum considered to be due at the date the notice is given and the basis on which that sum has been calculated. A JCT contract must also be satisfied with the minimum of the information required. A Pay Less notice must meet minimum of $1,500 and it should include: a ‘Pay Less Notice’ and an ‘Account for the amount’ is required to be made. A Notice must be detailed enough for the recipient to understand that the amount is not considered ‘unjustifiable’.



What monies can be deducted for with a Pay Less Notice?

Many reasons to reduce value of payment due to time between payment notice and Payment notice. Payee may have caused Payer to lose value due to non-payment due to issues during payment notice. These can range from minor issues to more significant problems like failure to complete works on site. The Payer may have suffered significant Loss and Expense resulting in the Payer’s loss and loss of pay-to-payments…


How does it work?

Standard contractual conditions require payment every month for several months of work carried out online or offline. A company that completes work (payer) checks and submits a monthly payment application to its client (payer). Client examines progress and confirms disagreement with the amount of Application Payments. This is done through payment notices confirming the amount the company has paid. The following example shows the steps for a Contract between a Main Contractor and a Subcontractor. 7 days later these were the normal monthly procedures described above.

How does it work?

A Pay Less Notice is a written notification from a Payer to a Payee of the Payer’s intention to pay less than the value stated in both their previous Payment Notice and/or the Payee’s application. It’s something which can lead to disputes and commercial friction. The issuance of a Pay Less notice can be something which can cause commercial disputes. We’ve created an example of the stages below based on a contract between a Main Contractor and a Subcontractor: 7 days later. It would be the same thing as 7 days before the Final Date for Payment as below: In our example, the Pay Less. Notice would be issued by the Main Contractors to the Subcontractors confirming they intend to pay…




Is there a time limit for JCT contracts?

It has time limits, but depends on what JCT contract you work for as this is varied by the standard form. If your contract has no time limit for the issuer or a payment less notice the Act becomes the precedent. Under Article 144 of this contract the Act provides: “The payment is payable in less than five days of the payment.” With contractual law please be aware some companies may change the statutory stated period of 7 days and the contractual arrangement will be negotiated on such terms and conditions.




What constitutes a valid Pay Less Notice?

Failure to provide the appropriate level of detail can be considered null and void in Adjudications and the Courts. If a Pay Less Notice is not issued on time and in compliance with the contract and the relevant legislation, it must be paid. The last notified sum is the amount of the Payment Notice. Notices follow certain minimum requirements to be declared as valid as required by courts and Adjudication. The Payment Notice is also required to be mad…



Pay less notices and what to do when you receive one

A pay less notice is the opportunity for a paying party to change their mind on payment. Despite the detailed statutory law on payment in construction contracts being in place for 10 years, it is still not always understood and leaves many confused. It means your payment is being legally reduced and potentially have a dispute. If you disagree with the notice that you have received, but the notice is valid, then formal proceedings such as adjudication becomes the only option open. The law is not set in stone and you can challenge the notice but you need professional help to take your payment dispute forward. If a dispute arises the payer will not stand down the notice if validly served, it will need to be challenged formally, mostly by adjudication….


Tell me the amount of money that can be deducted from a pay less notice?

The payer could be obligated to reduce the amount due on the basis of the fact that the amount was due between its receipt of payments and its receipt. They may be issues that payees suffered from because they suffered losses or expenses which can vary in size from minor items like the damage on the site to larger issues such as failure to carry out the work at the site.

For more articles like this, please sign up to our newsletter.

FAQs

When should a pay less notice be issued?

A pay less notice should be issued when the payer intends to pay less than the amount stated in a payment notice. It must be served within the time frame specified in the contract, typically before the final date for payment.

How do you challenge or dispute a pay less notice?

To challenge a pay less notice, you should respond in writing, outlining the reasons for disputing the notice. You may need to provide evidence or calculations supporting your claim. If the issue isn’t resolved, consider seeking legal advice or using alternative dispute resolution methods, such as adjudication.

Can you revise a pay less notice?

Yes, a pay less notice can be revised, but the revised notice should be issued within the contractual time frame. Ensure that the revised notice clearly states the new sum due, reasons for the change, and the basis for calculating the revised amount.

What is the difference between a payment notice and a pay less notice?

A payment notice is a document issued by the payer or payee, specifying the sum due for a specific payment period. A pay less notice, on the other hand, is issued by the payer when they intend to pay less than the amount stated in the payment notice. It should detail the reasons for the reduced payment and the basis for calculating the new sum.

Also see our article on How to Handle Unfair Payment Tactics


Leave a Comment